Work Program Status & Close-Outs
Program Year: 2015
Status: Close-Out
DC Project #: PM0C3A
FAP: 2015004
FMIS end date: none
Funding Attributes
- AY: 01
- Index: K0399
- PCA: 8000D
- OBJ: 0409
- Fund: 0350
- Note for all reqs: PT: 2709 Request is consistent with approved work plan, with line items revised per process approved in discussions between FHWA and DDOT after original obligation.
Program Actions
Work Plan
Obligation
PO Close-Out
- All outstanding invoices paid
- Budget status confirmed with HU Stephanie Dock (Unlicensed)
- Letters prepared and sent to HU Stephanie Dock (Unlicensed)
- Packet Tracker entry created Stephanie Dock (Unlicensed)
Program (FAP) Close-Out
- PO close-out complete
- Final acceptance form signed
- Final reports
- Final invoices
- Packet Tracker entry created
Program notes
Program Year: 2017
Status: Close-Out
DC Project #: PM0L6A
FAP: 2017014
FMIS end date:
Funding Attributes
- AY: 2001
- Index: K0832
- PCA: 8000D
- OBJ: 0409
- Fund: 0320
- Note for all reqs: PT: 4096, 5407 Request is consistent with approved work plan, with line items revised per process approved in discussions between FHWA and DDOT after original obligation.
Program Actions
Work Program
Obligation
PO Close-Out
- All outstanding invoices paid
- Budget status confirmed with HU
- Letters prepared and sent to HU
- Packet Tracker entry created
Program (FAP) Close-Out
- PO close-out complete
- Final acceptance form signed
- Final reports
- Final invoices
- Packet Tracker entry created
Program notes
Program Year: 2020
Status: Close-Out
DC Project #: PM0R8A
FAP: 2020005
FMIS end date:
Funding Attributes
- AY: 01
- Index: K1337
- PCA: 8000D
- AGY/OBJ: 0409
- Fund: 0320
- OAPT: 27352
- line 43 - projects
- line 44 - main program
- Note for all reqs: PT: 6336 Request is consistent with approved work plan.
Program Actions
Work Program
Obligation
PO Close-Out
- All invoices paid
- Budget status confirmed with HU
- Letters prepared and sent to HU
- Packet Tracker entry created
Program (FAP) Close-Out
- PO close-out complete
- Final acceptance form signed
- Final reports
- Final invoices
- Packet Tracker entry created
Program notes
- Project end date extended from 4/30/21 to 9/30/2021 in April 2021
Program Year: 2021
Status: Active
DC Project #: PM0T8A
FAP: 2021005
FMIS end date:
Funding Attributes
- AY: 01
- Index: K1494
- PCA: 8000D
- AGY/OBJ: 0409/0409
- Fund: 0320
- OAPT: 31293
- line 86 - projects
- line 85 - main program
- Note for all reqs: PT: 7523 Request is consistent with approved work plan.
Program Actions
Work Program
- Original: Budget and Work Program drafted
- Revision #1: budget and work program updated, 1365 prepared
- Revision #2: budget and work program updated, PAR for PS to NPS rebudget (no 1365 or work plan amendment form)
- 1365 for end date extension - link up with PAR action?
Obligation
- Original - PT: 7523
- PAR + Labor calc
- Environmental form
- Budget summary by line
- PAR + Labor calc
- End date extension PT:
- Combo PAR
- Signed 1365
PO Close-Out
- All invoices paid
- Budget status confirmed with HU
- Letters prepared and sent to HU
- Packet Tracker entry created
Program (FAP) Close-Out
- PO close-out complete
- Final acceptance form signed
- Final reports
- Final invoices
- Packet Tracker entry created
Program notes
Work Program dates:
- Original: conditionally approved 12/9/2020
- Revision #1: amendment accepted 8/11/2021 (swapped research projects)
- Revision #2: March 2022 - no approval needed because adding QR projects+only reallocating between lines
- 1365 end date extension from 4/30/2022 to 2/28/2023 due to pilot/quick response projects still in procurement - sent TBD (March/April), approved TBD
Program Year: 2022
Status: Active
DC Project #: PM0X4A
FAP: 2022006
FMIS end date:
Funding Attributes
- AY: 01
- Index:
- Line 101: K1641
- Line 102: K1642
- Line 103: K1643 (assumed)
- PCA: 8000D
- AGY/OBJ: 0409/0409
- Fund: 0320
- Note for all reqs: PT 8157 Request is consistent with approved work plan.
Program Actions
Work Program
- Original: Budget and Work Program drafted
- Revision #1: budget and work program updated, work plan amendment form prepared Stephanie Dock (Unlicensed)
Obligation
- Original - PT: 8157
PO Close-Out
- All outstanding invoices paid
- Budget status confirmed with HU
- Letters prepared and sent to HU
- Packet Tracker entry created
Program (FAP) Close-Out
- PO close-out complete
- Final acceptance form signed
- Final reports
- Final invoices
- Packet Tracker entry created
Program notes
Work Program dates:
- Original: conditionally approved 8/20/2021
- Revision #1: submitted 3/10/2022, approved TBD - added projects
Program Year: 2023
Status: not yet proposed
DC Project #: PM0
FAP:
FMIS end date:
Funding Attributes
Program Actions
Work Program
- Original: Budget and Work Program drafted
Obligation
- Original - PT:
- Work program approved by FHWA
- Environmental form signed
- Combo PAR
- Budget summary with lines for OCFO to load
- Work program approved by FHWA
PO Close-Out
- All outstanding invoices paid
- Budget status confirmed with HU
- Letters prepared and sent to HU
- Packet Tracker entry created
Program (FAP) Close-Out
- PO close-out complete
- Final acceptance form signed
- Final reports
- Final invoices
- Packet Tracker entry created
Program notes
Work Program dates:
- Original: